Oracle moves gas by trucks to keep its AI data centres on schedule

https://media.thenextweb.com/2026/09/oracle-sign-lit-at-night-bucharest.jpg

Oracle is trucking compressed natural gas to AI data centres that cannot yet connect to a pipeline, at roughly four times the price of gas at a hub. Europe has the same grid bottleneck and is answering it the other way, with Spain proposing to refuse connections to any data centre not on 80% renewables every hour.

Oracle is trucking compressed natural gas to data centres it cannot plug in. Road deliveries kept a site outside Salt Lake City moving for more than a year while it waited for a pipeline, and are powering early work at an OpenAI campus in Shackelford County, Texas. The shares fell about 5.5%.

New Mexico is next. Oracle is weighing the same approach at Project Jupiter, where the New Mexico State Land Office refused rights-of-way for Energy Transfer’s pipeline twice and the start date slipped to February, Bloomberg reported. Oracle did not reply...

Copyright of this story solely belongs to thenextweb.com. To see the full text click HERE

Read more

https://www.reuters.com/resizer/v2/AFZRO3UZENIB7DYPEYDI6K4PVQ.jpg?auth=658d59e5a02e2d11eb91644541b68655214c386c8a97e94cf743c085d036c070&height=1005&width=1920&quality=80&smart=true

The US Commerce Department says it began probing Megaspeed in 2024 over possible export rule violations; Nvidia put Megaspeed on its “no sell” list in June 2025

Featured Podcasts Big Technology Podcast: How Humans Will Work Alongside AI Agents — With Mike Cannon-Brookes The Big Technology Podcast takes you behind the scenes in the tech world featuring interviews with plugged-in insiders and outside agitators. Subscribe to Big Technology Podcast. Why Enterprise Sales Still Matters in the AI Era