Finland orders Google to stop clearing forest at two data centre sites

https://media.thenextweb.com/2026/10/google-hamina-data-centre-frozen-gulf-of-finland-dusk.jpg

Finland’s Licensing and Supervision Agency (LVV) has ordered Google’s Finnish subsidiary to stop work at two planned data centre sites, in Muhos and Kajaani. The halt covers work that significantly changes the environment. The agency issued the order on Tuesday.

Tuike Finland Oy must stop at once, and by 23 October at the latest. The halt lasts until the environmental impact assessments (EIA) for both projects are complete.

The order covers tree felling, topsoil removal, digging, quarrying, crushing, moving soil, ditching and building site roads and storage areas. Planning, measurements, soil surveys and other minor work that is easy to reverse can go on. Tuike has until 14 October to explain itself in writing. The agency can follow up with enforcement measures, including a conditional fine.

“In our assessment, these measures change the environment and cause impacts that the EIA procedure is meant to identify and assess,” said Tommi...

Copyright of this story solely belongs to thenextweb.com. To see the full text click HERE

Read more